The Santa Maria Public Airport’s runway extension project is being extended. The project had been scheduled for completion by April 5, but because of delays the full 8,000-foot runway won’t be open to air traffic until May 3, and it won’t be certified by the Federal Aviation Administration until May 31, according to General Manager …